Madison Ave and Haefner Drive Roundabout

The Haefner Drive and Madison Avenue intersection is currently under construction and will be closed for 2-3 months while crews construct a roundabout at the intersection. Traffic will be detoured around the intersection using Carver Road, Bassett Drive, and Highway 22. Access will still be maintained for those travelling to businesses. 

Clear business access signs will be placed during construction, but the following maps have been made available to help visitors depending on whether they're visiting businesses on the north or south side of the construction area:
North Side Business Access Map
South Side Business Access Map

The addition of a roundabout will improve safety, minimize delay, and improve access into and out of the surrounding business area. The roundabout will also accommodate future projected traffic volumes and support the growth in this area. 

For information regarding the project's design process, visit the Haefner Roundabout design site

Construction Updates

August 23, 2019
The bituminous paving has started and should be completed early next week. Roundabout median plantings and the lighting system should be installed next week. The remaining concrete work (medians, pedestrian ramps, sidewalk, driveways) is scheduled for late next week. A tentative opening date should be available once the schedule for the remaining work items (pavement markings, signage, seed, sod) is determined.

August 16, 2019
The concrete curb & gutter and the roundabout concrete truck apron have been installed. Portions of the bituminous trail have been paved. Bituminous roadway pavement and lighting should begin next week.

 August 8, 2019
All underground pipes have been installed. The sand sub-base is also complete and aggregate base should be completed this week. Concrete curb & gutter placement is currently scheduled to begin middle of next week.

July 31, 2019
Significant rains have slowed construction progress over the last couple weeks. Sand sub-base placement will begin this week. The remaining shallow storm sewer will be installed next week.

July 16, 2019
All storm sewer work should be complete early next week. Sanitary manhole liners are also being installed. Placement of the sand sub-base west of Haefner Drive should begin later next week.

June 24, 2019
Pavement removal and water main repairs are complete. Roadway excavation is underway to allow storm sewer installation to begin. Roadway excavation and storm sewer work is scheduled to continue through mid to late July. 

June 17, 2019
The intersection of Madison Avenue and Haefner Drive was shutdown on Monday, June 17th. Pavement removal has started (see included photo) and hydrant relocation is scheduled for the end of the week. Temporary water services will be installed by the middle of next week so water main repairs can be made. The included maps show the access routes to businesses near the project.