Madison Ave and Haefner Drive Roundabout

The Haefner Drive and Madison Avenue intersection is currently under construction and will be closed for 2-3 months while crews construct a roundabout at the intersection. Traffic will be detoured around the intersection using Carver Road, Bassett Drive, and Highway 22. Access will still be maintained for those travelling to businesses. 

Clear business access signs will be placed during construction, but the following maps have been made available to help visitors depending on whether they're visiting businesses on the north or south side of the construction area:
North Side Business Access Map
South Side Business Access Map

The addition of a roundabout will improve safety, minimize delay, and improve access into and out of the surrounding business area. The roundabout will also accommodate future projected traffic volumes and support the growth in this area. 

For information regarding the project's design process, visit the Haefner Roundabout design site

Construction Updates

June 24, 2019
Pavement removal and water main repairs are complete. Roadway excavation is underway to allow storm sewer installation to begin. Roadway excavation and storm sewer work is scheduled to continue through mid to late July. 

June 17, 2019
The intersection of Madison Avenue and Haefner Drive was shutdown on Monday, June 17th. Pavement removal has started (see included photo) and hydrant relocation is scheduled for the end of the week. Temporary water services will be installed by the middle of next week so water main repairs can be made. The included maps show the access routes to businesses near the project.